Warehouse Division Firewalls

Main Contractor

Background

Building on a successful long-standing working relationship with the main contractor, Stancold returned to warehouse units in Banbury to install fire-rated partitions and ceiling panels. Having previously worked on all units across the site, our familiarity with the facility enabled us to provide bespoke, project-specific design advice from the outset.

Process

The installation required 150mm thick composite wall and ceiling panels with a mineral fibre core to achieve the client’s specified fire ratings. Full fire-stopping was installed at all junctions where firewall and ceiling panels met adjacent structures (including external cladding and roofing) to ensure a safe installation was achieved.

Key project challenges included:

  • Installing 4.10m high firewalls around a projecting gantry/walkway in the unit requiring careful planning for difficult access conditions
  • Mid-project instruction to supply and install additional fire-rated partitions to ground floor levels in both units

Project Delivery

Stancold’s technical expertise was critical in overcoming the challenging access requirements. Our team successfully installed the 4.10m high firewalls around the projecting gantry, adapting installation methods to work safely within the constrained conditions.

When the client instructed additional fire-rated partitioning mid-project, our established relationship and on-site experience allowed us to provide targeted design advice for the new requirements. We designed solutions that integrated seamlessly with the existing infrastructure and react quickly and efficiently. We integrated the scope change seamlessly, completed all additional works within the client’s original programme requirements without delay.

Our ability to provide bespoke design solutions, adapt to evolving project needs, and maintain delivery schedules demonstrates the value of our collaborative, long-term partnerships with trusted contractors.

 

 

An example of Stancold adapting to new requirements within the original timescale.

James Cowmeadow, Stancold Project Manager
LocationBanbury
Building UseWarehouse
Panel CoreMineral Cored Fibre Panel
Panel SupplierEuroclad
Panel Thickness150mm
Panel Requirements185m²
ServicesProject Specific Design Advice
Correct Specification, Detailing of Each Product
Load/Span Calculations
Development of Bespoke CAD Details
Project Management 
Installation