Firewalls To Divide Office & Warehouse, A&H Construction, Oxfordshire

A&H Construction

Background

We have worked with A&H Construction on several occasions, and have worked on all the units at this site.

Process

Stancold installed a 150mm thick composite wall & ceiling panels with a mineral fibre core to both units to achieve the required fire ratings. We also installed firestopping products within the wall lines where the firewall/ceiling panels met adjacent structures (such as external cladding and roofing) to ensure the fire integrity of the installation was achieved.

Solution

Stancold dealt with difficult access conditions in Unit 7 by installing 4.10m high firewalls around a projecting gantry/walkway from the wall line. The sheer size of the panels in Unit 7 required extra care and attention to ensure a safe installation was achieved.

Half-way through the project, the client instructed Stancold to supply and install additional fire-rated partitions to the ground floor levels in both units. Stancold reacted quickly and efficiently to ensure these additional works were complete within the client’s original programme requirements.

Contact Shaun Jones with your enquiry

An example of Stancold adapting to new requirements within the original timescale.

James Cowmeadow, Stancold Project Manager
LocationBanbury
Building UseWarehouse
Panel CoreMineral Cored Fibre Panel
Panel SupplierEurobond
Panel Thickness150mm
Panel Requirements185m²
ServicesProject Specific Design Advice
Correct Specification, Detailing of Each Product
Load/Span Calculations
Development of Bespoke CAD Details
Project Management 
Installation