One-Hour Fire-Rated Partition for New Industrial Unit, Swindon

Main Contractor

Background 

As the Swindon industrial park underwent an expansion, Stancold won the tender to complete the sub-dividing fire-rated partitioning work in a new unit on the site.

Process

Stancold formed a new relationship with the main contractor throughout the project. Discussing the benefits of a composite panel system was a key element within the negotiation process, along with the contractor’s budget and quick turnaround time.

Stancold’s firewall team were able to value engineer a proposal that took their requirements into consideration.

Solution

Due to the height of the building, a horizontal panel installation was required, where approximately 700m² of the Eurobond Mineral Fibre Firemaster system was utilised to achieve a one-hour fire-rating for the partition. Intumescent batt was installed to the top and sides of the wall to maximise fire integrity and was completed with a painted deflection head detail.

With only four weeks between the initial pre-let meeting and our arrival on site, both Stancold’s office-based projects team and on-site installers worked hard to prepare and complete the build to the contractor’s schedule and to their complete satisfaction.

Contact Shaun Jones with your enquiry

Exceptional work by Stancold in keeping to our client's requirements

James Hoy, Stancold Contracts Manager
LocationSwindon
Building UseIndustrial
Panel CoreMineral Fibre
Panel SupplierEurobond
Panel Thickness100mm
Panel Requirements700m²
ServicesTechnical Drawings
LPS Approved Installation
Project Management