2-Hour Fire-Rated Warehouse Partitioning for Logistics Provider

Howard Tenens

The Brief

Howard Tenens, a nationwide logistics provider, required a reconfiguration of their large-scale storage and distribution facility In Berkeley following the acquisition of a new beverages contract.

Our Approach

The project required a 2-houre fire rated partition wall spanning the entire 70m width of the facility.

Key project challenges included:

  • Designing a compliant installation solution around substantial existing racking infrastructure across the full 70m span
  • Engineering a unique head detail to achieve the required fire rating within the building’s structural constraints
  • Delivering a phased installation to coordinate with concurrent demolition works on site

Delivery in Action

During planning our team evaluated the space and decided that installing the panels horizontally would work around the existing racking on site with minimal disruptions. We advised using a Euroclad paneling system to ensure the 2-hour fire rating would be met.

Stancold installed the 70m long x 8m high partition wall using Euroclad Firemaster Extra panels, achieving the full 2-hour fire rating. Fireboarding was applied to existing steel columns throughout, with a bespoke head detail designed specifically to meet the fire rating requirements within the building’s unique structural constraints.

The installation was carefully phased across two stages, allowing demolition works to be completed before the final section was handed over.

The completed installation gave Howard Tenens the fire-rated reconfiguration they needed to confidently take on their new contract.

We're very pleased with the wall and its final look and finish

Glyn Loveday, Howard Tenens
Location Berkeley
Building Use Logistics
Panel Core Mineral Fibre
Panel Supplier Euroclad
Panel Thickness 100mm
Panel Requirements 525m²
Services Design Advice
LPS Approved Installation
Construction Drawings