Firewall & A Non-Fire-Rated Enclosure

Fit-Out Contractor

Background

Stancold were approached by an office fit-out company requiring assistance with the composite partitioning scope of their works for leading confectionery & sweets manufacturer Swizzles’ new facilities in Cheshire.

Following a successful tender process Stancold were awarded the contract to deliver an 84-metre long, 120-minute fire-rated wall and the construction of a non-fire-rated enclosure for a processing room.

Process

Our sales and design teams consulted the client’s architects to propose a solution that accommodated the existing steelwork structure. Following a site visit to advise on possible up-rating of fire-rated elements already in place, Stancold specified a vertically oriented wall made of two stacked rows of Euroclad panels, optimising both the fire rating and integration with the building’s structural framework.

The main project challenges included:

  • Designing an 84-metre long, 120-minute fire-rated wall around existing steelwork
  • Coordinating phased site visits in line with other contractors’ programmes
  • Constructing a specialist enclosure for flammable starch-processing operations

Project Delivery

Our technical expertise and collaborative approach ensured the specification met both the fire safety requirements and the operational needs of a sensitive food manufacturing environment.

The Stancold team liaised closely with the client to coordinate our visits in line with other works on site, allowing for flexible delivery of the overall project. Using Euroclad panels, we successfully constructed the 84-metre long, 120-minute fire-rated wall, complete with up-rated fire protection on existing elements.

A month later, our team returned to site to construct a 150m² non-combustible enclosure to contain the starch-processing plant. Given the flammable nature of starch, keeping this area separate from the rest of the facility was essential, and our composite panel solution provided the containment and protection required while maintaining operational efficiency.

A great showcase of how we can help a contractor deliver their turnkey project

Rob White, Stancold Project Manager
LocationCheshire
Building UseSweets Manufacturing
Panel CoreQuadcore, Mineral Fibre
Panel SupplierKingspan, Euroclad
Panel Thickness100, 125, 150 mm
Panel Requirements1490 m²
ServicesConsultative Approach
Specification Development
Multi-Disciplinary Expertise