Multi-Phase Fire-Rated Warehouse Dividing Walls

A&H Construction

Background

Having completed similar projects in the past, our client and principal contractor approached Stancold to deliver a three-phase firewall project across newly constructed warehouse facilities in London, creating compliant fire separation between commercial warehouse spaces and office areas.

Process

The project required 1-hour fire-rated partition walls across three new-build warehouses, delivered in phases to align with the construction programme. The project came with its challenges including a curved roof profile, but Stancold’s flexible systems ensured we were able to fully meet the client’s expectations.

Main project challenges included:

  • Complex curved roof profiles requiring flexible installation solutions
  • Multi-phase delivery demanding coordination with other trades
  • Full fire-stopping compliance and secondary steelwork integration

Project Delivery

Stancold successfully delivered all three phases on programme, utilising a bespoke galvanised channel detail to support panels directly to the mezzanine structure. This enabled full-span panel installation, eliminating additional steelwork painting and delivering cost savings with a superior aesthetic finish.

The curved roof profile was seamlessly accommodated thanks to the flexibility of our partition system, demonstrating our ability to adapt engineering solutions to challenging architectural features while maintaining full fire compliance.

The installation work is absolutely exemplary.
Everything went as planned.

Andy Sutton, A&H Construction
LocationLondon
ProjectWarehouse Dividing Walls
Building useIndustrial & Office Building
Panel coreMineral Fibre
Panel supplierEuroclad
Panel thickness125mm & 150mm
Fire rating1 hour
Panel requirements1,730 m²
OtherFirestopping: Intumescent Batt