Factory Expansion Firewall & Office Installation for Production Factory

Rehau

The Brief

Building on the success of a previous project, Rehau approached us to support with their factory expansion to allow for their new production line.

Our Approach

The project required a 1-hour firewall to separate production from the existing factory that needed to be accessible through two fire-rated personnel doors. The expansion also required a series of office spaces, including one with a mezzanine floor, to support the expanded operations.

To achieve this, our team advised on Euroclad composite panels for the firewall installation due to their proven fire performance. We advised on Kingspan panels for the office spaces to provide a suitable work environment for staff.

This needed to be completed within a strict timeframe of 2 weeks to allow for minimal operational disruptions for the end user.

Delivery in Action

Through close coordination and regular communication with the factory manager, our team successfully installed the firewall, fire-batting, and door openings in just 4 days which allowed Rehau to maintain productivity throughout.

The office spaces were carefully designed to integrate into the existing layout while providing a suitable, comfortable working environment for staff. All elements were completed on schedule, demonstrating our ability to deliver quality installations even within the constraints of a live operational facility.

The offices were designed to fit into the existing spaces and provide a suitable working environment for staff.

 

Successful regular communication for an efficient installation

Lee Duffield, Project Manager, Stancold
Location Wales
Building Use Specialist Production
Panel Core Mineral Fibre
Panel Supplier Euroclad
Kingspan (Offices)
Panel Thickness 150mm (Firewall)
80mm (Offices)
Panel Requirements 1085m²
Services Project Specific Design Advice
Load/Span Calculations
Development of Bespoke CAD Details