Background

Stancold were approached by interior fit-out contractor, Fuselek, to complete the design and build of a fire-rated corridor, as part of larger works for a food manufacturing facility less than 5 miles from Stancold’s head office in Bristol.

Process

Designed to provide access to three newly formed labs, the corridor required a one-hour fire-rating, with a mezzanine floor constructed above, to follow on after our works. On Stancold’s doorstep, a site visit confirmed access points and the feasibility of the proposed installation method. The team’s trusted expertise of composite panel systems for fire-rated applications made sure that each of the design, specification and build elements could work together to achieve the required solution.

Project Delivery

Stancold’s industrial partitioning team utilised Eurobond’s Firemaster composite panel system, in 150mm thickness, to construct the fire-rated walls and ceiling, thus achieving the FR60 certification. Our LPS-approved installers completed the contract in just one week, enabling the next phase of site works to continue smoothly.

Contact Shaun Jones with your enquiry

Stancold's fire-rated expertise has been demonstrated once again

Rob White, Contracts Manager
LocationBristol
Building UseFood Manufacturing
Panel CoreMineral Fibre
Panel SupplierEurobond
Panel Thickness150mm
Panel Requirements143m²
ServicesValue Engineered Solutions
Unrivalled Technical Expertise
Fire-Rated Design Support