Warehouse Office Compartment Walls

Barnwood Ltd

Background

Following our work with local main contractor, Barnwood, on successful industrial projects in the past, Stancold were invited to tender for another composite firewall package within a new BREEAM ‘Very Good’ rated industrial unit in Gloucester.

Process

Stancold’s Industrial Partitions team successfully secured the competitive tender to supply and install LPCB-approved FR60 office compartment walls within the new-build warehouse.

Project Delivery

Our LPS-accredited installation team completed the build of 600m² of the one-hour-fire-rated compartment walls, including all firestopping at the sides and head of the steelwork.

A horizontal panel installation was followed for the composite walls, thanks to the building’s existing steelwork structure, enabling our construction programme to be handed over in three weeks, in line with Barnwood’s wider schedule of works.

An LPCB certificate of conformity was issued to confirm the fire resistance of the build.

Contact Shaun Jones

It was a pleasure to work with Barnwood locally once again

Shaun Jones, Industrial Partitions Specialist
LocationGloucester
Building UseIndustrial Warehousing
Panel CoreMineral Fibre
Panel SupplierTrimo
Panel Thickness150mm
Panel Requirements602m²
ServicesLPS-Accredited Installation
Turnkey Construction Package
Unrivalled Technical Expertise