1-Hour Fire-Rated Warehouse Compartmentation For New Tenants

Howard Tenens

Background 

Stancold were delighted to be approached again by property owners, Howard Tenens following our previous work together at their site in Berkley site. For this new project we were asked to help with modifications to their new vacant warehouse site in Swindon to prepare for new tenants.

Process

To maximise the building’s lettable potential, Howard Tenens planned for two new compartment walls to divide the large warehouse space into three distinct, compliant units.

The main project challenges included:

  • Designing fire-rated division walls that accommodated the vast yet elongated shape of the warehouse
  • Completing the works within a strict 1-week timeframe

Project Delivery 

Our established relationship with the client allowed us to get straight to work. We carried out an immediate site survey so that our design team could create a bespoke solution that suited the shape of the warehouse, choosing Euroclad Mineral Fibre paneling with 100mm thickness as the most suitable option to achieve the desired fire rating.

With the building unoccupied, Stancold had the space to work efficiently. We successfully constructed the 2 partition walls to compartmentalise the unit with additional fire boarding to protect the existing steelwork and maintain fire integrity.

The swift, seamless delivery met Howard Tenens’ requirements and prepared the warehouse for its next chapter.

A seamless install from start to finish

Paul Towse, Stancold Project Manager
LocationSwindon
Building UseLogistics
Panel CoreMineral Fibre
Panel SupplierEuroclad
Panel Thickness100mm
Panel Requirements194m²
ServicesDetailed Design Advice
Full Site Surveys
Expert Product Knowledge