As a part of the continued development of CREST’s range of services, we are proud to report we recently completed our first non-progressive cleanroom envelope build, following training and familiarisation with the MIDDAS system.
“Bouygues brought us on board with specification & layout almost confirmed between themselves, the specified panel manufacturer, MIDDAS, and the customer”, says Mark Kendrick, CREST’s Business Development Director.
“Even with the above agreed upon, we conducted multiple site surveys to advise on buildability from a cleanroom envelope specialist point of view. The scope also required alterations within the existing lab and included a one-hour fire-rated wall, something best left to partitioning specialists to advise on.”
“The client knows our capabilities – this was a project not many subcontractors could successfully take on”, starts Lee Duffield, CREST Construction Director. “Not only was it a live site, but it included many different elements – the lab fit out itself, a firewall, complex layout of lining panels, reveals, and on top of everything, breaking into the existing clean area to reconfigure it. All of it within a fast-track programme.”
Our installation team completed the extension in 6 weeks proving its versatility in intricate projects.
Read more about the MIDDAS Bi-Panel Partitioning System here or email info@crestcleanrooms.co.uk for expert consultation.