Background

Stancold’s food projects team were appointed as the internal fit-out contractor by leading industrial construction company, Minshall Construction, as part of a site redevelopment for an award-winning food ingredients supplier.

Process

Over a construction programme of three phases, Stancold were required to undertake the food-safe fit-out of a new-build extension, the installation of a blast freezer and reconfiguration works to an existing production area.

The team were able to advise on appropriate design changes to suit the services already in place and navigate complexities around a large bulkhead section to the first floor.

Project Delivery

Over the course of 18 months, Stancold collaborated closely with Minshall Construction to successfully complete the works in line with the scheduled programme, taking an approach that allowed the client to start operating in finished areas while others were still in progress.

Our package included the installation of both insulated and fire-rated composite panel systems, vision panels and doors to form high-risk and low-risk areas, airlocks and offices, all complete with a food-safe finish to fulfil the required safety standards and an aesthetically ‘clean’ fit-out throughout.

The team’s dedicated experience and understanding of constructing in live food manufacturing environments ensured that the delivery of this project met the end user’s expectations.

Contact Patrick Ball

A food production facility transformed through this phased schedule of works

Sam Glover, Senior Contracts Manager
LocationWales
Building UseFood Ingredients Manufacturing
Panel CoreQuadCore; Mineral Fibre
Panel SupplierKingspan; Eurobond
Panel Thickness100mm
Panel Requirements1710m²
ServicesPhased Construction Programme