FM Approved Cleanroom Upgrade

Electronic Components Manufacturer

The Brief

A global manufacturer of electronic components for the automotive sector needed to upgrade the cleanroom at its Bedford facility to satisfy revised insurance conditions.

The requirement was specific: an FM Approved cleanroom system, supplied and installed by an architectural envelope contractor with the technical credentials to evidence compliance, and delivered without taking production offline.

Our Approach

Following a site visit to establish the full scope, Stancold proposed the removal of the existing cleanroom walls and their replacement with the FM Approved Puracore system, including all doors and vision panels.

The client’s operational commitments shaped every decision. Key challenges included:

  • Maintaining production throughout, with only a 10-day shutdown of the main cleanroom agreed
  • Meeting FM Approval requirements in full to satisfy the updated insurance conditions
  • Working safely and cleanly within a live, classified environment
  • Areas of the existing envelope that could not be assessed until removal began

Delivery in Action

Working within a live cleanroom demanded a stringent construction programme and daily health and safety briefings to manage personnel moving in and around the works area.

Where the original surveys could not reach concealed sections of the existing envelope, our site and in-house design teams worked in real time to identify issues and reissue drawings, resolving them as they arose rather than pausing the programme.

The flexibility of the Puracore system, combined with Stancold’s experienced installation teams, allowed on-site adaptations to be made without compromising the specification. Drawing on 2,188m² of 50mm aluminium honeycomb panelling supplied for the works, the upgraded cleanroom handed over within 12 weeks on site, bringing the facility into line with its insurers’ requirements.

LocationBedford
Building UseElectronic Components Production
Panel SystemPuracore
Panel CoreAluminium Honeycomb
Panel Thickness50mm
Panel Requirements2,188m²
Specialist ExpertiseFM Approved Cleanroom Systems
Live Environment Construction