Background:

A turnkey contractor enlisted Stancold to deliver the cleanroom envelope for a Deeside pharma extension, where the existing Kingspan system would be complemented by the specified MIDDAS non- progressive panels and associated framework.

Fortunately, Stancold’s team has extensive experience delivering this type of cleanroom envelope project.

Process:

The team collaborated with MIDDAS and the contractor to design the envelope, reworking the Kingspan layout to form a lobby and incorporating fire rated MIDDAS panels.

MIDDAS offers their panel systems with a mineral fibre core to satisfy fire-rated requirements.

Project Delivery:

Over four weeks on site, Stancold installed the cleanroom layout, combining the existing Kingspan system with a bespoke MIDDAS framework for the extension, including a gowning room and lobby, and complete with the specified MIDDAS doors and vision panels.

Stancold also managed the installation of a Kingspan vision panel and infill panel in the existing space of the facility.

Our team values any opportunity to further our experience with non-progressive cleanroom panel systems like MIDDAS.

Our team reliably delivers cleanroom envelope builds using either a progressive panel system or a non‑progressive system such as MIDDAS.

Mark Kendrick, Business Development Director
LocationDeeside
Building UsePharmaceutical Development
Panel CorePlasterboard; Plasterboard w/ Internal Mineral Fibre Core
Panel SupplierMIDDAS
Panel Thickness100mm
Panel Requirements320m²
ServicesUnrivalled Technical Expertise
Coordination with Multiple Contractors
Utilisation of Multiple Panel Systems