Cleanroom Reconfiguration

Specialist Coatings

Background:

After a prior successful installation, CREST were approached directly to reconfigure 25% of the previous cleanroom installation to allow for larger equipment to be installed.

Process:

Due to the size of the new larger machinery, as part of the scope, the team were required to design and build a new bulkhead in accordance with the existing facility plan.

Not only did the walls and ceilings of the selected area need to be redesigned, but the fire escape system and refrigeration airflow systems also needed to be updated to accommodate the new area layout.

Project Delivery:

Upon arrival, the team faced a strict two-week shutdown to accommodate our work. The team’s ability to work flexibly to the client’s needs further allowed for a planned phased construction. Once the machinery was in place, the team returned to the site to complete the build.

The team also reconfigured the site’s airflow system to ensure the correct temperature and air control was in place.

The team ensured the safety of the pre-existing manufacturing equipment by maintaining a controlled environment by sectioning them off, creating a clean and secure workspace.

The team have been incredibly flexible in their working conditions, we couldn’t be more proud of them.

Steve Gunning, CREST Contract Manager
LocationStaffordshire
Building UseWound Care Manufacturing
Panel CoreQuadCore
Panel SupplierKingspan
Panel Thickness50mm, 100mm
Panel Requirments410m²
ServicesPlanned Phased Construction
Enclosed Working Environment
Colour Matched Systems
Bulkhead Design And Build