ISO 7 Cleanroom

Monmouth Scientific

 

Background:

Having built a strong relationship with clean air solutions experts, Monmouth Scientific, CREST were appointed to work alongside them on a new cleanroom for a high-end precision mouldings manufacturer for their new injection moulding facility.

Process:

To align with updated product specifications and meet stringent regulatory requirements, the new cleanroom facility had to achieve ISO Class 7 certification in accordance with ISO 14644-1 standards.

The cleanroom was set to be split into three separate rooms, each with personnel doors, and a sliding door for ease of access

Project Delivery:

Due to our team’s extensive product knowledge, they were able to install thicker ceiling panels to comply with the specification of the HEPA air filtration system. Collaborating with a trusted expert such as Monmouth Scientific was essential to guarantee system integrity, regulatory compliance and long-term reliability of the clean air environment.

Across the cleanroom itself, a laminated finish was applied to the panels for ease of maintain a clean and sterile environment.

Furthermore, the team installed vision panels in each room, making it easier for staff and clients to oversee production without needing to enter the cleanroom. The vision panels would allow for enhanced day-to-day monitoring, support smoother communication and provide a clear view of operations at a glance.

The fast-track contract, which was completed in under a week, left both Monmouth Scientific and their client satisfied.

Installer team were very good and end user was very happy.

David Pomeroy, Monmouth Scientific
LocationRoss on Wye
Building useCustom Injection Moulding
Panel CoreQuadCore
Panel SupplierKingspan
Panel Thickness80mm, 150mm
Panel Requirements250m²
ServicesFast-Track Package
On-Site Flexibility
Trusted Client Relationship
Expert System Knowledge