Sterile Finish Cleanroom
E-liquid Manufacturer
Background:
With the growing popularity of e-cigarettes and vapes, our client, an e-liquid manufacturer, required a cleanroom refurbishment to adhere to recent industry regulations.
Process:
As part of the scope, the client required the cleanroom to fit into a pre-existing space with limited headroom due to the mezzanine above.
Additionally, a gowning room was required in order for staff to change into the appropriate PPE in an airlocked room to maintain the stringent conditions of the sterile facility.
Project Delivery:
Due to the height restrictions, CREST were required to be flexible in their approach and used their expert knowledge to aid in the selection of suitable panels, taking into consideration the weight of the client’s equipment and apertures.
The insulated ceiling within the cleanroom was designed to be self-supporting to allow for service apertures and provide suitable thermal efficiency.
CREST’s skilled team completed the contract in align with the client’s timescale and left them satisfied with the outcome.

The end product looks amazing! We are very happy with how it all went.


| Location | Birmingham |
|---|---|
| Building use | E-Liquid Production |
| Panel core | PIR |
| Panel Supplier | Hemsec |
| Panel Thickness | 80mm & 100mm |
| Panel Requirement | 169m² |
| Services | Tight Construction Build |
| On-Site Flexibility | |
| Specialist Installation Team | |
| Fast-Track Programme |