Beverage Processing Area Upgrade, Kegworth

Drinks Producer

Background 

Stancold have worked with this bottled drinks producer for many years on their Somerset site, and thanks to a number of successful projects there, we were recommended to undertake works within their Kegworth facility.

Process

As part of the required upgrade works, Stancold were asked to install full-height food-safe partitions to form a process area, ingredients room, handwash station and cold store. The specification also included an airlock between existing storage space and the new processing area. Our team were able to recommend materials and ancillaries that best suited the developing design, while planning a schedule that co-ordinated with the client’s dedicated shutdown period.

Solution

Stancold’s installation team worked hard on site to complete over 1700m² of partitioning works using the Kingspan Quadcore panel system, complete with a food-safe laminate finish. This project included the integration of 4 rapid rise doors and 3 personnel doors, along with 2 large vision panels for free viewing between areas. All exposed original steelwork was encased with white food-safe cladding to create an aesthetically-pleasing finish and match the surrounding fit-out. Our team demonstrated reliability and delivered vital product expertise to successfully achieve the desired design specification for these works.

Contact details for Patrick Ball, Divisional Development Manager

The whole team that installed the Kingspan walling, performed professionally throughout the project

Project Engineer, Drinks Producer
LocationKegworth
Building UseDrinks Manufacturer
Panel CoreQuadCore
Panel SupplierKingspan
Panel Thickness100mm; 125mm
Panel Requirements1738m²
ServicesProgramme Coordination
Full Project Management
Unrivalled Installation Expertise