Abattoir Facility Fit-Out, Sheffield

Meat Producer

Background

Stancold’s Food Projects Team was approached by a construction company, working on behalf of a meat producer based in Sheffield, to fit out the producer’s abattoir facility.

Process

Multiple whitewall partitioned areas were required to suit the end user’s operations, alongside a visitor gallery complete with vision panels for PPE-free abattoir viewing.

Project Delivery

Stancold were able to install the requested whitewall partitions and the viewing room adherent to the design agreed upon by all parties. The construction schedule was altered by the end user due to unforeseen circumstances, but we stayed on hand and were able to finish the project efficiently and thoroughly once they were ready for the installation to continue.

The project ended up requiring a complex system of hygienic whitewall panelling and over twenty specific door fit-outs. Despite the schedule alterations by the end user, Stancold made sure to see this installation through to the end, working with the main contractor and end user’s timelines. We were pleased to do our part in getting the abattoir up and running for the facility’s end user.

We were happy to accommodate the end user’s schedule to get this project completed.

Sam Glover - Stancold Project Manager
LocationSheffield
Building UseAbattoir Facility
Panel CoreQuadcore
Panel SupplierKingspan
ServicesBespoke Whitewall Panel Installation
Unrivalled Technical Expertise
Flexible Scheduling Around The Client's Needs